| OWNER OR CONTRACTOR MOWING | ENFORCEMENT MOWING |
| CYCLE 1 -- March 15 to March 23 | March 24 |
| CYCLE 2 -- April 26 to May 4 | May 5 |
| CYCLE 3 -- June 7 to June 15 | June 16 |
| CYCLE 4 -- July 12 to July 20 | July 21 |
| CYCLE 5 -- August 16 to August 24 | August 25 |
| CYCLE 6 -- September 20 to September 28 | September 29 |
| CYCLE 7 -- October 18 to October 26 | October 27 |
| CYCLE 8 -- November 22 to November 30 | December 1 |
Mowing Specifications
- Eight (8) field mowing cycles have been established by the Las Colinas Association. Adjoining public rights-of-way must be included.
- Mowing height is not to exceed a maximum of six (6) inches.
- Trimming must be provided around all items a minimum of twenty (20) feet back of street curbs and property lines adjacent to developed sites. Utility boxes further than twenty (20) feet away from the curb must be trimmed around.
- Curbs must be edged – grass and dirt must be swept/blown out of the street.
Limbs, litter, and debris must be removed from the property.
- Only those portions of field tracts containing active growth of spring wildflowers may remain unmowed. To avoid enforcement mowing, owners should notify the Association of their intentions.
Program Operation
The Las Colinas Association administers the annual field mowing program and defines adequate mowing maintenance of undeveloped lots and field condition expansion areas as adherence to the above specifications.
If mowing, trimming, and curb maintenance are not provided prior to each enforcement date, the Association will hire a contractor to perform the needed work at the owner's expense. (Ref.: Article VI, Las Colinas Declaration).
|
|
|